Archive for the ‘PHOTOS’ Category
Tiles around the pool
May 13th, 2008
Works are going on the swimming pool place with the tiles:
If you need more details about the gites and the pool, do not hesitate to contact us:
- 00 33 (6) 23 00 13 67
- contact@horizons-vendeens.fr
Works are going on in both gites
May 10th, 2008
Little by little, gites start taking shape! Before long, restoration works will come to a close, craftspeople make way for tourists…
Below, photos show you the screed in the gite 2, which has covered the heating floor and that has being dried since 2 weeks. One week more, the tiles will be put down.
In the gite 1, photos are more scarce but after these finishing touches, see below the ground floor of this gite, more particularly the mezzanine with its quiet spot -on the left, while coming up the stairs- and its space for children -on the right, above the kitchen. Now we should furnish this place but above all, secure it with a banister made of wrought iron.
For further details about gite and pool, do not hesitate to contact us either by mail contact@horizons-vendeens.fr or by phone -00 33 (0)6 23 00 13 67
Soon, in the 1st gite, photos will show you the kitchen, that will be ended in the following days…
Week’s works in the gite & pool
April 27th, 2008
After silence of one week in the posts for the “Horizons vendéens“, you can find below the summary of the works, which still go on!
-
Front stone wall-to-be of the gite 2
As already explained in the previous posts, the wall -”built with breeze blocks-which is located on the front façade of the gite 2, should be covered with stones. Hereafter, the following steps since last November:
After having laid the ”last” stones and the wood lintels on this wall of this gite, stoneworkers will make way for the workers for the stone face-lifting of this façade. Then, our website should be available on Internet…
-
Screed above the tiles in the gite 2
No photo can be available: indeed, the liquid screed was poured last Wednesday, so we should not walk on it for the moment and we should also avoid draughts in this gite because of risk of cracks inside the screed. Now wait and see for some weeks before the tiles can be seen on the floor…
-
Tiles in the pool area
All around the pool, in the changing room and also for the machines space, a “standard” screed has been poured and the tiler begins his work next week. Hereafter, photos of the screed:
-
Waste water from the gite 1 and from the gite 2
The waste water for the both gites and the changing room of the pool have been well connected to the town services. No photo should be needed to understand this part of work.
-
Earthworks begin in the back side of the gites and the pool
The earthworker ,as he was around the gites and the pool, began last week to level this surroundings, more precisely in the back side of the gites and the pool.
-
Ceilings in the gite 1
We have fallen the ceilings in rooms like bathrooms and toilets, but also in the living room and kitchen of the gite 1 so that all ceilings are the same and more precisely light. Indeed, we have choosen to lay white panellings so that all rooms should be bright at the most.
For further details about Horizons vendéens -gites & swimming pool- let us know by the following link: contact@horizons-vendeens.fr.
What about the heating in the 2nd gîte?
April 19th, 2008
Works in the gite 2 are going on with the plumber , with the heating floor…
Entrance hall of the gite:
Living room of the gite -in the quiet spot:
Living room of the gite:
Kitchen of the gite:
Corridor -view from bedrooms towards living room of the gite:
Bedrooms of the gite:
If you want more details about the gites and the pool, let us know with contact@horizons-vendeens.fr.
Walls inside the gite 2, the end!
April 16th, 2008
After cleaning out stones on 2 walls in the gite 2, and as explained in the post Walls inside the gite 2, we ought to strenghten the front wall of this gite -weakened- with a “grey coating”, then in order to avoid loosing too much place, we have choosen to get a coating instead of having placo with a finishing touch of paintwork , so the colour will be the same as the coating on the other walls of the living room.
Hereafter photos showing this finishing touch in this gite:
In order to have a more precise idea of the living room of this gite, any complementary photos:
For further information about Horizons vendéens -gites & swimming pool- let us know by the following link: contact@horizons-vendeens.fr.
Partitions in the 2nd gite
April 13th, 2008
In this gite, persons in charge of placo should create and demarcate rooms:
Partition between the living room and bedrooms of the gite:
Evolution of partitions for the bedrooms of the gite:
View from the living room towards bedrooms -on the left- and kitchen -on the right-
then in the background bathroom of the gite:
From bedrooms/bathroom towards kitchen and living room of the gite:
-on opposite view-
Do not hesitate to contact us if you need more exhaustive details about gites of Horizons vendéens and their common swimming pool with this following link contact@horizons-vendeens.fr.
What about the works in the pool?
April 11th, 2008
As far as the swimming pool is concerned, works are going on with the placo, which demarcate these 2 spaces, namely space for changing room -toiletd and shower- and one for the machines.
Hereafter different photos showing the development step by step:
On one hand, the changing room on the other hand, “room” for machines
Lastly, after technical information with placo, it should be good to see this following photo, taken recently towards the sight, when you go out the swimming pool from back of the stone buildings:
Do not hesitate to contact us if you need more exhaustive details about the gites and the swimming pool, contact@horizons-vendeens.fr.
Outside walls on the back of the gites & pool
April 7th, 2008
Styl’façades goes on cleaning out the stones and face-lifting the walls with the back of the stone buildings, starting with the gite 1, then on the swimming pool plac and at last on the gite 2.
the whole stone buildings -the 2 gites and the swimming pool:
the whole stone buildings: the 2 gites and the swimming pool -opposite view:
the gite 1:
the swimming pool place:
the gite 2: